Question 8 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in wee
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question 8 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in wee
Question 8 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b A 5 7 B 4 8 10 с 2 3 5 D 6 9 12 E 5 9 15 Table 9.2 Reference: Ref 9-2 Using Table 9.2, the expected time to complete the project is Select one: O A. 31.00 weeks. B. 34.17 weeks. O C. 33.23 weeks. O D. 21.67 weeks. 3 L.O Activity Predecessor A A B, C D