22 Medro will use the project network diagram shown (activity times are in weeks) to start a summer camp for children. H

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

22 Medro will use the project network diagram shown (activity times are in weeks) to start a summer camp for children. H

Post by answerhappygod »

22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 1
22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 1 (56.16 KiB) Viewed 37 times
22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 2
22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 2 (32.04 KiB) Viewed 37 times
22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 3
22 Medro Will Use The Project Network Diagram Shown Activity Times Are In Weeks To Start A Summer Camp For Children H 3 (53.63 KiB) Viewed 37 times
22 Medro will use the project network diagram shown (activity times are in weeks) to start a summer camp for children. He prepared a table for the project with all the necessary information. He would like to crash the project to 21 weeks. Which of the following is the correct crashing plan? (6 Points) K 6 6 M 2001 8 Activity Max Crashing Normal Cost Crash Time Crash Cost Time (weeks) Crashig Cost/week (KD/week) (KD) (weeks) (KD) A 100 7 100 X 80 140 Y 200 250 K 6 110 110 Z 8 300 6 330 L 3 60 3 60 M 7 150 3 190 a. crash M, Z, X for a total crashing cost of 90 KD b. crash A, X, Z, M for a total crashing cost of 760 KD c. crash X, Y, Z, M for a total crashing cost of 660 KD d. none of the above START A7 Normal Time (weeks) 7 6 5 3 3 6
21 Medro sat down and thou about his daily capacity for making mini cheesecakes during the first few months of opening. He believes the design capacity for making mini cheesecakes will equal to 120 cakes/day and the effective capacity will equal to 100 cakes/day. If he believes that the system utilization will be 80%, what will the system efficiency be equal to? (6 Points) a. 80% b. 96% c. 100% d. not enough information to solve e, none of the above
20 Medro's labor productivity last week was 20 sandwiches/hour. This week it was 25 sandwiches/hour. What was the growth rate? (6 Points) The table below shows the number of units Medro thinks he can sell in a week for coffee drinks, sandwiches, and cheesecakes. Coffee Drinks Sold Sandwiches Sold Cheesecakes Sold 800 400 200 The number of employees required to produce each output is shown below: Coffee drinks Sandwiches Cheesecakes 7 employees 6 employees 3 employees The selling price for each output is shown below: Coffee drinks Sandwiches Cheesecakes 2 KD/unit 4 KD/unit 3 KD/unit The labor cost for each employee is 200 KD/week Overhead cost = 2x(the total labor cost) a. 5% b. 20% c. 25% d. none of the above
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply