Page 1 of 1

Given the figure below, operation 4 represents a rework operation on parts that fail in- spection upon completion of ope

Posted: Sun Jun 05, 2022 9:48 pm
by answerhappygod
Given The Figure Below Operation 4 Represents A Rework Operation On Parts That Fail In Spection Upon Completion Of Ope 1
Given The Figure Below Operation 4 Represents A Rework Operation On Parts That Fail In Spection Upon Completion Of Ope 1 (132.43 KiB) Viewed 47 times
Given the figure below, operation 4 represents a rework operation on parts that fail in- spection upon completion of operation 2. 1 2 3 5000 Units d₂ = 5% d₁ = 5% d3 = 10% 4 d4 = 2% How many units must the process start with in order to meet the required output of 5000 units?