Given the figure below, operation 4 represents a rework operation on parts that fail in- spection upon completion of ope
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Given the figure below, operation 4 represents a rework operation on parts that fail in- spection upon completion of ope
Given the figure below, operation 4 represents a rework operation on parts that fail in- spection upon completion of operation 2. 1 2 3 5000 Units d₂ = 5% d₁ = 5% d3 = 10% 4 d4 = 2% How many units must the process start with in order to meet the required output of 5000 units?