For the netwrok diagram below: A. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure b
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
For the netwrok diagram below: A. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure b
For the netwrok diagram below: A. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project. Can the project be completed in 37 weeks? B. Assume that activity A actually finished at 3 weeks, activity B actually finished at 12 weeks, and activity C actually finished at 13 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule and finish in 37 weeks? Activity Actuy Activity A Activity D Activity G Activity Activity C Activity 10
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!