Use The Following Information For Problems I Through 5 Activity Immediate Normal Normal Time Predecessor S Cost S 1 (39.83 KiB) Viewed 17 times
Use The Following Information For Problems I Through 5 Activity Immediate Normal Normal Time Predecessor S Cost S 2 (6.35 KiB) Viewed 17 times
Use the following information for Problems I through 5. Activity Immediate Normal Normal Time Predecessor(s Cost (S) ) (weeks) A none 10 16,000 B none 4 6,000 C A, B 6 12,000 D A 7,000 E B 28,000 F C, D, E 4,500 G F 7,200 H F 5,000 I 15,000 J 7,000 K 10,000 L 24,000 F H, I J K 7 14 3 4 2 5 2 5 10 Crash Time (weeks) 8 3 3 5 12 3 3 2 4 2 4 10 Crash Cost ($) 20,000 9,000 24,000 10,000 34,000 4,500 5,000 18,000 7,000 11,000 24,000
2. Calculate the critical path and the project completion time for the project.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!