Use the following information for Problems I through 5. Activity Immediate Normal Normal Predecessor(s Time Cost (S) ) (
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Use the following information for Problems I through 5. Activity Immediate Normal Normal Predecessor(s Time Cost (S) ) (
5. If the company wants to complete the project in 40 weeks, which activities should be crashed? Calculate the additional cost incurred to complete the project in 40 weeks. Foot