Use the following information for Problems I through 5. Activity Immediate Normal Normal Predecessor(s Time Cost (S) ) (weeks) A none 10 16,000 B none 4 6,000 C A, B 6 12,000 D A 7 7,000 E B 14 28,000 F C, D, E 3 4,500 G F 4 7,200 H F 5,000 I F 15,000 J H, I 7,000 K J 10,000 L K 24,000 1. Draw the network diagram. 2 5 2 5 10 Crash Time (weeks) 8 3 3 5 12 3 3 2 4 2 4 10 Crash Cost ($) 20,000 9,000 24,000 10,000 34,000 4,500 9,000 5,000 18,000 7,000 11,000 24,000
5. If the company wants to complete the project in 40 weeks, which activities should be crashed? Calculate the additional cost incurred to complete the project in 40 weeks. Foot
Use the following information for Problems I through 5. Activity Immediate Normal Normal Predecessor(s Time Cost (S) ) (
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Use the following information for Problems I through 5. Activity Immediate Normal Normal Predecessor(s Time Cost (S) ) (
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!