Page 1 of 1

QUESTION 8 8. Which one is wrong? O A. CPM and PERT are essentially network-oriented techniques using the same principle

Posted: Mon May 30, 2022 9:07 am
by answerhappygod
Question 8 8 Which One Is Wrong O A Cpm And Pert Are Essentially Network Oriented Techniques Using The Same Principle 1
Question 8 8 Which One Is Wrong O A Cpm And Pert Are Essentially Network Oriented Techniques Using The Same Principle 1 (17.35 KiB) Viewed 27 times
QUESTION 8 8. Which one is wrong? O A. CPM and PERT are essentially network-oriented techniques using the same principle. O B. PERT and CPM are basically time-oriented methods in the sense that they both lead to determination of a time schedule for the project. O C. The significant difference between two approaches is that the time estimates for the different activities in CPM were assumed to be deterministic while in PERT these are described probabilistically. O D. These techniques are referred as project scheduling techniques. O E. In CPM activities are not shown as a network of precedence relationships using activity-onnode network construction