QUESTION 8 8. Which one is wrong? O A. CPM and PERT are essentially network-oriented techniques using the same principle
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 8 8. Which one is wrong? O A. CPM and PERT are essentially network-oriented techniques using the same principle
QUESTION 8 8. Which one is wrong? O A. CPM and PERT are essentially network-oriented techniques using the same principle. O B. PERT and CPM are basically time-oriented methods in the sense that they both lead to determination of a time schedule for the project. O C. The significant difference between two approaches is that the time estimates for the different activities in CPM were assumed to be deterministic while in PERT these are described probabilistically. O D. These techniques are referred as project scheduling techniques. O E. In CPM activities are not shown as a network of precedence relationships using activity-onnode network construction