Activities A (3-4) B (3-5) C (3-6) D (3-7) Duration, month 536 2 Earliest Start 6 6 6 6 Latest Start 6 6 6 6 Earliest Fi
Posted: Mon May 30, 2022 9:05 am
15. Considering table given in question 13, 4 activities may start at the same time. But only two activities could start at the same time at the scheduling day due to the limited resources. Which activities should be postponed? O A-) B and D O B-) A and C O C-) A and B O D-) A and D O E-) C and D