Activities A (3-4) B (3-5) C (3-6) D (3-7) Duration, month 536 2 Earliest Start 6 6 6 6 Latest Start 6 6 6 6 Earliest Finish 11 13 12 12 Latest Finish 11 19 17 16
15. Considering table given in question 13, 4 activities may start at the same time. But only two activities could start at the same time at the scheduling day due to the limited resources. Which activities should be postponed? O A-) B and D O B-) A and C O C-) A and B O D-) A and D O E-) C and D
Activities A (3-4) B (3-5) C (3-6) D (3-7) Duration, month 536 2 Earliest Start 6 6 6 6 Latest Start 6 6 6 6 Earliest Fi
-