QUESTION 4: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing

Posted: Mon May 30, 2022 9:04 am
by answerhappygod
Question 4 C Two Jobs Must Be Processed Through A Five Machine Shop The Processing Times Are Shown Below The Routing 1
Question 4 C Two Jobs Must Be Processed Through A Five Machine Shop The Processing Times Are Shown Below The Routing 1 (38.75 KiB) Viewed 17 times
QUESTION 4: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing of the jobs are as follows: J1 M4, M5, M₁, M², M2 J2 M5, M4, M₁, M2, M2 Machine Job M₁ M₂ M3 M₁ M5 J₁ 4 4 8 2 6 J₂ 2 5 7 4 3 a) (20 points) Using the graphical approach, find the minimum makespan schedule, and interpret it. What is the value of Cmax? (Solving by other methods will not be evaluated!) b) (5 points) Calculate the total waiting times of J₁ and J₂.