QUESTION 4: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 4: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing
QUESTION 4: C. Two jobs must be processed through a five-machine shop. The processing times are shown below. The routing of the jobs are as follows: J1 M4, M5, M₁, M², M2 J2 M5, M4, M₁, M2, M2 Machine Job M₁ M₂ M3 M₁ M5 J₁ 4 4 8 2 6 J₂ 2 5 7 4 3 a) (20 points) Using the graphical approach, find the minimum makespan schedule, and interpret it. What is the value of Cmax? (Solving by other methods will not be evaluated!) b) (5 points) Calculate the total waiting times of J₁ and J₂.