Astec Company is preparing budgets for the coming year. 120,000 labour hours will be 100% level of expected productive

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Astec Company is preparing budgets for the coming year. 120,000 labour hours will be 100% level of expected productive

Post by answerhappygod »

Astec Company is preparing budgets for
the coming year. 120,000 labour hours will be 100% level of
expected productive time, but a flexible budget at 90%, 110% and
120% is required so that cost allowances can be set for these
possible levels.
Budgeted costs
details
Fixed Costs per
annum
$
Depreciation
22,000
Staff
salaries
43,000
Insurances
9,000
Rent and
Rates
12,000
Variable Costs
Power
$0.30 per direct labour hour
Consumables
$0.05 per direct labour hour Direct
labour
$3.50
per direct labour hour
Semi-Variable
Costs
Analysis of past records, adjusted to
eliminate the effect on inflation shows the following:
Direct labour
hours
Total Semi-variable cost
Last year
6
110,000
$330,000
Year
5
100,000
305,000
Year
4
90,000
280,000
Year
3
87,000
272,500
Year
2
105,000
317,500
Year
1
80,000
255,000
Required:
A Cost Budget at 100% and flexed to
show cost allowances at 90%, 110% and 120%