Use the following information to answer questions #45 through #50. A 3-year project will cost $60,000 to construct. This

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Use the following information to answer questions #45 through #50. A 3-year project will cost $60,000 to construct. This

Post by answerhappygod »

Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 1
Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 1 (29.33 KiB) Viewed 11 times
Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 2
Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 2 (5.56 KiB) Viewed 11 times
Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 3
Use The Following Information To Answer Questions 45 Through 50 A 3 Year Project Will Cost 60 000 To Construct This 3 (21.9 KiB) Viewed 11 times
Use the following information to answer questions #45 through #50. A 3-year project will cost $60,000 to construct. This will be depreciated straight-line to zero over the 3-year life. Projected sales = 7,000 units per year, price per unit-$25 and variable cost per unit-$14. Fixed costs $30,000 per year. The tax rate=30% and the debt-to-equity ratio is 1. The firm has outstanding 8% annual coupon bonds with 9 years until maturity selling at 109:0. The firm just paid a $2.00 dividend on its common stock, the dividend growth rate is 5% and the stock currently sells for $28 per share. 60,000-0/3 45. What is the operating cash flow in year 22 = 20,000 27,000 (30) = 8,100 &$18900 7,000 (25-14) = 77,000 b. 27,000 -8,100-18.900 18,900 + 20,000 c. $34000 77,000-30,000 = 47,000 4,000 -20 000 = 29,000 $38900 MUST e. None of the above. Correct answer = 38,900 isioner LE of
OWGI 49. What is the NPV of the project? (Assume the appropriate discount rate is 9,57%)
to pu is wi IS swe a $7656 b. $17360 c. $37475 d. $67475 e. None of the above. Correct answer 50. What is the discounted pay-back period? (Round to higher year) a. 0 years b. 1 year c. 2 years d. 3 years e. None of the above. Correct answer