A certain project requires a total volume of concrete equal to 2 000 m3 and requires. Determine the total cost to comple

Posted: Fri May 27, 2022 7:42 am
by answerhappygod
A certain project requires a total volume of concrete equal to 2 000 m3 and requires.
Determine the total cost to complete the (per. cu.m.) of this project.
A Certain Project Requires A Total Volume Of Concrete Equal To 2 000 M3 And Requires Determine The Total Cost To Comple 1
A Certain Project Requires A Total Volume Of Concrete Equal To 2 000 M3 And Requires Determine The Total Cost To Comple 1 (34.33 KiB) Viewed 18 times
4. A certain project requires a total volume of concrete equal to 2 000 m³ and requires: Item Description Rates Concrete pump Php. 3,000/hr rental Pump rated working output 100 m³/day Working hours of pump 8 hrs/day 1 Operator Php. 85/hr 2 Finishing Masons Php. 65/hr each 4 Carpenters Php. 60/hr each 6 Laborers Php. 50/hr each Determine the total cost to complete the project and calculate the unit cost (per. cu.m.) of this project. (20 pts)