A certain project requires a total volume of concrete equal to 2 000 m3 and requires.
Determine the total cost to complete the (per. cu.m.) of this project.
4. A certain project requires a total volume of concrete equal to 2 000 m³ and requires: Item Description Rates Concrete pump Php. 3,000/hr rental Pump rated working output 100 m³/day Working hours of pump 8 hrs/day 1 Operator Php. 85/hr 2 Finishing Masons Php. 65/hr each 4 Carpenters Php. 60/hr each 6 Laborers Php. 50/hr each Determine the total cost to complete the project and calculate the unit cost (per. cu.m.) of this project. (20 pts)