3. (a) An extract of the corridor through a railway scheme is shown in Figure 2. It requires cutting of the existing gro

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

3. (a) An extract of the corridor through a railway scheme is shown in Figure 2. It requires cutting of the existing gro

Post by answerhappygod »

3 A An Extract Of The Corridor Through A Railway Scheme Is Shown In Figure 2 It Requires Cutting Of The Existing Gro 1
3 A An Extract Of The Corridor Through A Railway Scheme Is Shown In Figure 2 It Requires Cutting Of The Existing Gro 1 (138.83 KiB) Viewed 15 times
3 A An Extract Of The Corridor Through A Railway Scheme Is Shown In Figure 2 It Requires Cutting Of The Existing Gro 2
3 A An Extract Of The Corridor Through A Railway Scheme Is Shown In Figure 2 It Requires Cutting Of The Existing Gro 2 (25 KiB) Viewed 15 times
3. (a) An extract of the corridor through a railway scheme is shown in Figure 2. It requires cutting of the existing ground levels between chainages 0+200 to 0+380 to the formation level of the subgrade. The cross-sectional area at each chainage is given in the diagram and the average swell factor of the soil is 1.25. It is intended to use 2 excavators, each having 1.6m³ bucket capacity; and 2 number 18 m³ dumper trucks. Using relevant calculations, establish which of the two scenarios below is a faster option and by how many weeks to complete the works: (i) one dumper truck assigned to each excavator (ii) two excavators filling one dumper truck at a time Existing levels A = 150m² Chainage 0+200 A = 225m² Chainage 0+230 A = 355m² Chainage 0+260 A = 405m² Chainage 0+290 A = 158m² Chainage 0+320 A = 255m² Chainage 0+350 A = 505m² Chainage 0+380 Formation levels Figure 2 Corridor of railway and cross-sectional areas at cutting chainages.
You may assume the following Excavator bucket has 75% fill capacity and output is 75 cycles per hour. • Dumper truck travel and repositioning time is 4.5 minutes. ● A working day is 8 am - 4 pm with an hour-long break. 5 working days per week ●