Part 5 Use the plan view of the specified differential leveling operation to create complete field notes with all necessary information and calculations. Provide a mathematical check of your work in the field notes. The circles along the level line indicate instrument setups. The numbers are foresight and backsight readings from the instrument. P6-10 See Figure P6-10 9. BM 2 7.84 7.59 4.11 9.14 BM 1 496.92 Figure P6-10
Figure P6-10 P6-11 See Figure P6-11 0. BM 2 1.692 8.105 3.011 2.066 4.621 11.384 7.550 9.4413 BM 1 496.92