Complete the Matrix for the following 4 jobs which have arrived at 4 machines on a first due first. All times are in hou

Posted: Sat May 21, 2022 9:37 am
by answerhappygod
Complete The Matrix For The Following 4 Jobs Which Have Arrived At 4 Machines On A First Due First All Times Are In Hou 1
Complete The Matrix For The Following 4 Jobs Which Have Arrived At 4 Machines On A First Due First All Times Are In Hou 1 (48.63 KiB) Viewed 16 times
Complete the Matrix for the following 4 jobs which have arrived at 4 machines on a first due first. All times are in hours. Assume there is always work in the system before and after these 4 jobs Job Due M/C 1 M/C 2 M/C 4 MIC 3 4 А 5 2 07 B Week 6 Week 5 Week 7 4 6 3 3 с 4 8 5 5 D 4 6 LO 4 7 Week 3 M/c1 M/c2 M/c3 M/c4 Job A Job B Job C Job D What is the throughput of the jobs? Evaluate the queuing time of the jobs waiting for machines to become available? Evaluate the time the machines are stopped and waiting for work