Complete the Matrix for the following 4 jobs which have arrived at 4 machines on a first due first. All times are in hou
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Complete the Matrix for the following 4 jobs which have arrived at 4 machines on a first due first. All times are in hou
Complete the Matrix for the following 4 jobs which have arrived at 4 machines on a first due first. All times are in hours. Assume there is always work in the system before and after these 4 jobs Job Due M/C 1 M/C 2 M/C 4 MIC 3 4 А 5 2 07 B Week 6 Week 5 Week 7 4 6 3 3 с 4 8 5 5 D 4 6 LO 4 7 Week 3 M/c1 M/c2 M/c3 M/c4 Job A Job B Job C Job D What is the throughput of the jobs? Evaluate the queuing time of the jobs waiting for machines to become available? Evaluate the time the machines are stopped and waiting for work