- Hw 2 Consider The System Shown Schematically In The Figure 1 The System Supplies A Load From The Main Generator Throug 1 (71.29 KiB) Viewed 34 times
HW #2 Consider the system shown schematically in the Figure 1; the system supplies a load from the main generator throug
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
HW #2 Consider the system shown schematically in the Figure 1; the system supplies a load from the main generator throug
HW #2 Consider the system shown schematically in the Figure 1; the system supplies a load from the main generator through step up transformer (TX), if the main generator is failed, the switch (S) should be connected with the backup system that consist of 2 generators are required for 100% system success, each one supply 50% of the load, Construct the events tree of the system. And then calculate the unreliability of the system if the reliability of transformer is 1.0 and all generators and switch are identical with a reliability of 0.95. Gen 1 TX S Main Gen. Gen 2 load Figure 1