Project A and B involve the following net cash flows: Year 0 1 2 3 4 -5, 000 -50 200 Project A Project B 2, 000 13,000 7,000 1,500 -12, 000 -5, 000 6,000 What is the net present value of project B, if interest rate is 7% per annum? NPV P. (1 + )