4/12 - 1645 + H Part II: Short and Long Answer Questions. (64 points in total) 1. A project can be described by the foll
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
4/12 - 1645 + H Part II: Short and Long Answer Questions. (64 points in total) 1. A project can be described by the foll
Questions. (64 points in total) 1. A project can be described by the following table: Activities Immediate Predecessor Duration (Days) Slack Time (Days) 4 А 3 B A 2 с B S 3 D A 4 E CD 5 F DE 4 (a) Construct a network diagram to depict the project. (3 points) (b) Fill in the slack time in the table. (3 points with 0.5 point for each blank) (c) What is the critical path? (2 points) MacBook Pro ay R 7 U o Zol-2 112 2 delete G Р K 2 & N a