64. A Planner is attempting to calculate the cumulative lead time needed to supply a finished good item. She/he gathers
Posted: Fri May 20, 2022 9:27 am
64. A Planner is attempting to calculate the cumulative lead time needed to supply a finished good item. She/he gathers the following historical data: supplier lead time for the components - 30 days receiving & inspection lead time - 5 days components sat in stockroom inventory - 40 days pick and issue lead time - 1 day assembly and final test lead time - 5 days finished goods sat in inventory - 10 days The cumulative lead time based on the above data is : 41 days 51 35 61 0 91