- 64 A Planner Is Attempting To Calculate The Cumulative Lead Time Needed To Supply A Finished Good Item She He Gathers 1 (36.55 KiB) Viewed 79 times
64. A Planner is attempting to calculate the cumulative lead time needed to supply a finished good item. She/he gathers
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
64. A Planner is attempting to calculate the cumulative lead time needed to supply a finished good item. She/he gathers
64. A Planner is attempting to calculate the cumulative lead time needed to supply a finished good item. She/he gathers the following historical data: supplier lead time for the components - 30 days receiving & inspection lead time - 5 days components sat in stockroom inventory - 40 days pick and issue lead time - 1 day assembly and final test lead time - 5 days finished goods sat in inventory - 10 days The cumulative lead time based on the above data is : 41 days 51 35 61 0 91