53. Ms Mona Hull is in charge of a project to build a 50-foot yacht for a customer. Eight weeks remain for constructing
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
53. Ms Mona Hull is in charge of a project to build a 50-foot yacht for a customer. Eight weeks remain for constructing
Question 55 1 pts 54. Using the same data in the previous problem (#53) - What is the critical ratio if only 2 out of the 10 operations are completed by Tuesday morning of week 3? 0.88 0.85 0.87 0.91
53. Ms Mona Hull is in charge of a project to build a 50-foot yacht for a customer. Eight weeks remain for constructing the yacht. Assume that each week consists of 5 workdays, for a total lead time of 40 days. The work required to complete the yacht comprises 10 operations, 4 days for each including move time between operations. On Tuesday morning of week 3, 3 of the 10 operations had been completed and the yacht was waiting for the fourth operation. What is the critical ratio priority? (rounded to two decimal places) Gantt might help you solve this problem. None of the answers provided. .97 1.04 1.00