A Hospital wants to forecast the number of patients tomorrow (5/12). The following is the information about the patients
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A Hospital wants to forecast the number of patients tomorrow (5/12). The following is the information about the patients
A Hospital wants to forecast the number of patients tomorrow (5/12). The following is the information about the patients in the previous days: Date 05/05 05/06 05/07 05/08 05/09 05/10 05/11 Patients 171 221 20 20 25 30 20 What is the forecasted number if the hospital uses a 5-day moving average method? 20 25 22 23