Given the following network, with activity times in months: 15 Start 8 7 10 6 12 (a) Determine all of the paths (4 Point
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Given the following network, with activity times in months: 15 Start 8 7 10 6 12 (a) Determine all of the paths (4 Point
Given the following network, with activity times in months: 15 Start 8 7 10 6 12 (a) Determine all of the paths (4 Points) (b) Which path is the critical path? (2 Points) (c) How long is the project duration? (2 Points)