Problem-5: The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard de
Problem-5: The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks. • What is the probability the project will be finished in 62 weeks or less? • What is the probability the project will be finished in 66 weeks or less? What is the probability the project will take longer than 65 weeks?