NETWORK DIAGRAM - PART 1 Consider the following information about a project: Activity Duration (days) Predecessors A 10
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
NETWORK DIAGRAM - PART 1 Consider the following information about a project: Activity Duration (days) Predecessors A 10
NETWORK DIAGRAM - PART 1 Consider the following information about a project: Activity Duration (days) Predecessors A 10 B 4 A С 12 A D 17 B,C E 16 D F 6 С G 14 F H 6 E,G After creating a complete two pass Network Diagram for this project in a sheet of paper with your name, answer how much is the total duration of this project in days?