Using the following project information, calculate the variance for each of the project activities. Optimistic Time Esti
Posted: Fri May 20, 2022 7:49 am
by answerhappygod

- Using The Following Project Information Calculate The Variance For Each Of The Project Activities Optimistic Time Esti 1 (26.43 KiB) Viewed 29 times
Using the following project information, calculate the variance for each of the project activities. Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) Activity A 2 3 Сл 5 none B 2.5 4 5 А с 5 7 00 8 A D 3 5 7 B.C E 3 6 14 B,C ח ד ם F 2 5 8 D G 4 5 6 E I Н. 6 6 8 F 1 5 7 10 G J 2 3 3 HI
(Round your answers to 2 decimal places, e.g. 1.75.) Activity Variance A B с D E F G H Н. 1 J