Using the following project information, calculate the variance for each of the project activities. Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) Activity A 2 3 Сл 5 none B 2.5 4 5 А с 5 7 00 8 A D 3 5 7 B.C E 3 6 14 B,C ח ד ם F 2 5 8 D G 4 5 6 E I Н. 6 6 8 F 1 5 7 10 G J 2 3 3 HI
(Round your answers to 2 decimal places, e.g. 1.75.) Activity Variance A B с D E F G H Н. 1 J
Using the following project information, calculate the variance for each of the project activities. Optimistic Time Esti
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Using the following project information, calculate the variance for each of the project activities. Optimistic Time Esti
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!