- An Organization Is Carrying Out A Project Construct The Network Activity Diagram Using The Following Information Activ 1 (88.95 KiB) Viewed 29 times
An organization is carrying out a project. Construct the network activity diagram using the following information: Activ
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
An organization is carrying out a project. Construct the network activity diagram using the following information: Activ
An organization is carrying out a project. Construct the network activity diagram using the following information: Activity A B C Predecessors None A Duration (Days) 4 4 A 2 D A Ол | 5 E C N F B 4 G E 2 NIN H E, F 2 1 3 D G, H, 1 J 4 a. Using AON notation, carryout both a forward and backward pass. b. What is the estimated total duration for the project? c. Identify all paths through the network. d. Which is the critical path? e. Which activities have slack time? f. Identify all burst activities and merge activities.