You are a Project Manager of a construction project. The
scope of the project is a construction of 5-floors building.
Planned cost of construction of one floor is $200,000 and time
needed for that is 2 months. The project sponsor asked you to
report about the status of the project at the end of 6th month of
the project. By using the Earned Value Management methodology,
please calculate SV and CV, if by that moment you have already
constructed four floors and spent $750,000. Using CPI
and SPI indexes, please report whether your project is ahead
or behind the schedule, and whether you have overspent or
underspent the budget.