Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

You are a Project Manager of a construction project. The scope of the project is a construction of 5-floors building. Pl

Post by answerhappygod »

You are a Project Manager of a construction project. The
scope of the project is a construction of 5-floors building.
Planned cost of construction of one floor is $200,000 and time
needed for that is 2 months. The project sponsor asked you to
report about the status of the project at the end of 6th month of
the project. By using the Earned Value Management methodology,
please calculate SV and CV, if by that moment you have already
constructed four floors and spent $750,000. Using CPI
and SPI indexes, please report whether your project is ahead
or behind the schedule, and whether you have overspent or
underspent the budget.