А manager wants to build 3-sigma x-bar control limits for a process. The target value for the mean of the process is 12
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
А manager wants to build 3-sigma x-bar control limits for a process. The target value for the mean of the process is 12
А manager wants to build 3-sigma x-bar control limits for a process. The target value for the mean of the process is 12 units, and the standard deviation of the process is 3. If samples of size 5 are to be taken, what will be the upper and lower control limits, respectively? 13 and 7 18 and 6 16 and 8 6 and 18 21 and 3