From the following information, develop an AON project network. Complete the forward and backward pass, compute activity
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? 10 Description Predecessor Tine Survey site 6 B Excavate site A 5 С Install power Lines D Install drainage Pour foundation C D А None B 4 1 3 E days The project will take The critical path is The late start on Activity Cis The slack on Activity is The slack on Activity Dis The early start on Activity is days days days days