- Given Daily Demand 50 With A Standard Deviation Of 4 Lead Time 2days Ordering Cost 100 Per Order Holding Cost 1 (26.48 KiB) Viewed 51 times
Given: Daily demand = 50 with a standard deviation of 4, lead time = 2days, ordering cost = $100 per order, holding cost
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Given: Daily demand = 50 with a standard deviation of 4, lead time = 2days, ordering cost = $100 per order, holding cost
Given: Daily demand = 50 with a standard deviation of 4, lead time = 2days, ordering cost = $100 per order, holding cost = $1 per unit per day, and safety stock of 5 units are required. 044 Find the optimal order quantity a. 100 b. 60 c. 80 d. 200 e. 120 Q45 Find the service level corresponding to the safety stock. Choose the closest answer if needed. a. 81% b. 96% c. 73% d. 89% e. 99%