Page 1 of 1

QUESTION 57 a) Draw the project network. b) Find the critical path activities. c) Calculate slack for ALL activities. d)

Posted: Fri May 20, 2022 6:33 am
by answerhappygod
QUESTION 57
Question 57 A Draw The Project Network B Find The Critical Path Activities C Calculate Slack For All Activities D 1
Question 57 A Draw The Project Network B Find The Critical Path Activities C Calculate Slack For All Activities D 1 (29.86 KiB) Viewed 36 times
a) Draw the project network.
b) Find the critical path activities.
c) Calculate slack for ALL activities.
d) How long will take to complete the project?
Activity A Predecessors NONE Time (days) 6 8 B А с BA 2 D А 3 E B 5 F 5 C,D E,F,D G 6