QUESTION 57
a) Draw the project network.
b) Find the critical path activities.
c) Calculate slack for ALL activities.
d) How long will take to complete the project?
Activity A Predecessors NONE Time (days) 6 8 B А с BA 2 D А 3 E B 5 F 5 C,D E,F,D G 6
QUESTION 57 a) Draw the project network. b) Find the critical path activities. c) Calculate slack for ALL activities. d)
-