QUESTION 57 a) Draw the project network. b) Find the critical path activities. c) Calculate slack for ALL activities. d)

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

QUESTION 57 a) Draw the project network. b) Find the critical path activities. c) Calculate slack for ALL activities. d)

Post by answerhappygod »

QUESTION 57
Question 57 A Draw The Project Network B Find The Critical Path Activities C Calculate Slack For All Activities D 1
Question 57 A Draw The Project Network B Find The Critical Path Activities C Calculate Slack For All Activities D 1 (29.86 KiB) Viewed 34 times
a) Draw the project network.
b) Find the critical path activities.
c) Calculate slack for ALL activities.
d) How long will take to complete the project?
Activity A Predecessors NONE Time (days) 6 8 B А с BA 2 D А 3 E B 5 F 5 C,D E,F,D G 6