The following table provides the information necessary to construct a project network diagram and project crash data: Ac

Posted: Fri May 20, 2022 6:06 am
by answerhappygod
The following table provides the information necessary to
construct a project network diagram and project crash data:
Activity
Immediate predecessor
Activity Time (weeks)
Activity Cost ($)
Normal
Crash
Normal
Crash
A
--
16
8
2000
4400
B
--
14
9
1000
1800
C
A
8
6
500
700
D
A
5
4
600
1300
E
B
4
2
1500
3000
F
B
6
4
800
1600
G
C
10
7
3000
4500
H
D, E
15
10
5000
8000
End
F, G, H