The following table provides the information necessary to construct a project network diagram and project crash data: Ac

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The following table provides the information necessary to construct a project network diagram and project crash data: Ac

Post by answerhappygod »

The following table provides the information necessary to
construct a project network diagram and project crash data:
Activity
Immediate predecessor
Activity Time (weeks)
Activity Cost ($)
Normal
Crash
Normal
Crash
A
--
16
8
2000
4400
B
--
14
9
1000
1800
C
A
8
6
500
700
D
A
5
4
600
1300
E
B
4
2
1500
3000
F
B
6
4
800
1600
G
C
10
7
3000
4500
H
D, E
15
10
5000
8000
End
F, G, H