Current Attempt in Progress At Paver, the standard quantity of labor is 24 hours per refrigeration unit. The standard wa
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Current Attempt in Progress At Paver, the standard quantity of labor is 24 hours per refrigeration unit. The standard wa
company produced 75 refrigeration units and incurred 2,130 labor hours at a cost of $63,900. Calculate the labor rate variance and the labor efficiency variance. Indicate whether the variances are favorable or unfavorable. (Round intermediate calculations to 2 decimal places, e.g. 14.37 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.) Labor Rate Variance 6390 Favorable Labor Efficiency Variance $
Current Attempt in Progress At Paver, the standard quantity of labor is 24 hours per refrigeration unit. The standard wage rate is $33. In July, the