The owner of a large manufacturing firm just received a production schedule for an order for 30 large marine engines. Ov
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
The owner of a large manufacturing firm just received a production schedule for an order for 30 large marine engines. Ov
company is to produce 2, 3, 5, 8, and 12 engines, respectively. The first unit took 3,000 direct labor hours, and experience on past projects indicates that a 95 percent learning curve is appropriate; therefore, the second unit will require only 2,850 hours. Estimate the total number of full-time employees needed each month for the next 5 months. Assume that each employee works 40 hours per week and that there are 365 days in this year, i.e. it is not a leap year. Hint: Find the average number of weeks per month. NOTE: Using a spreadsheet to help you with this question is a good idea, however you CANNOT simply submit a spreadsheet or a table of the results. We want to see a detailed set of hand calculations for ALL portions of the work as a proof of your solution.
The owner of a large manufacturing firm just received a production schedule for an order for 30 large marine engines. Over the next 5 months, the