9. Use the following road template and cross section notes to calculate the earth work quantity for the roadway between
Posted: Wed May 18, 2022 5:16 pm
9. Use the following road template and cross section notes to calculate the earth work quantity for the roadway between station 35 + 50 and 36 +00. Centerline grade at 35 + 50 is 887.0 and at 36+00 is 888.5. (50 pts) 27 25 Road Template 25 2% 2% 2:1 t -1.0 93.0 50 916 25 8904 36.00 900 89.0 15 50 X-Section Notes 923 50 90.0 20 889.5 35.50 90.0 20 880 50