9. Use the following road template and cross section notes to calculate the earth work quantity for the roadway between
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
9. Use the following road template and cross section notes to calculate the earth work quantity for the roadway between
9. Use the following road template and cross section notes to calculate the earth work quantity for the roadway between station 35 + 50 and 36 +00. Centerline grade at 35 + 50 is 887.0 and at 36+00 is 888.5. (50 pts) 27 25 Road Template 25 2% 2% 2:1 t -1.0 93.0 50 916 25 8904 36.00 900 89.0 15 50 X-Section Notes 923 50 90.0 20 889.5 35.50 90.0 20 880 50