The table below gives area information on earthwork of road cross sections at three different stations. The cumulative a
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The table below gives area information on earthwork of road cross sections at three different stations. The cumulative a
The table below gives area information on earthwork of road cross sections at three different stations. The cumulative amount of earthwork moved from station to station is most nearly: Station Cut (ft) Fill (Ft) Sta 5 +00 60 80 Sta 6 +35 120 150 Sta 8 + 65 200 210 O 2100 ya 3921 yos 1813 yd 2931 ya +