Create a construction network with the following conditions, specify the critical path, and Find the number of days requ

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Create a construction network with the following conditions, specify the critical path, and Find the number of days requ

Post by answerhappygod »

Create a construction network with the following conditions,
specify the critical path, and
Find the number of days required. (Indicate the first and
intermediate stages)
① Work activities A, B, and C are executed in parallel as the first
work of this construction.
② Tasks D and E are started only when task A is completed.
③ Task G is started only when tasks B, C, and E are
completed.
④ Task F is started only when tasks A and E are completed.
⑤ Task H is started only when tasks D, E, F, and G are
completed.
⑥ Task I is started only when tasks F and G are completed.
⑦ Tasks H and I are performed in parallel, and when they are
completed, the construction is finished.
⑧ The number of days required for each task is as follows.
A = 5 days, B = 10 days, C = 9 days, D = 20 days, E = 7 days,
F = 15 days, G = 16 days, H = 8 days, I = 5 days