A project has a contract price of $3,797,622. The cost to date is $1,097,162 and the estimated cost to complete is $2,24
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A project has a contract price of $3,797,622. The cost to date is $1,097,162 and the estimated cost to complete is $2,24
A project has a contract price of $3,797,622. The cost to date is $1,097,162 and the estimated cost to complete is $2,240,874. Based on this information, calculate the total gross profit recognized to date. Report your answer to the nearest dollar 166,081 151,059 margin of error +/- 5 Find the percent complete based on cost to date and re-estimated cost to complete. Find the estimated profit at completion based on the contract amount and the cost to date plus cost to complete. Use that percentage of the estimated profit at completion.