2. For the figures shown, calculate how many cubic yards of concrete are needed to construct the continuous footing and include 10% of waste for concrete material, and how many lineal feet of forms are needed to construct the continuous footing. Calculate how many cubic yards of concrete are needed to construct the wall and include 12% of waste for concrete material and how many square feet of forms are needed to construct the wall. Wall Section
16'-0" 14-8" 8-4" 2 x 4 WALL WITH 7/16" OSB 5/8"X 10" ANCHOR BOLT @ 32" 0.C 8-4" 24'-0" 8" 22-0 20-8" 0-8" 8-0" 12'-0" 12'-0" #4 REBAR @ 12" O.C. BOTH WAYS #5 DOWELS @ 12" O.C. ALTERNATING DIRECTIONS 2 EACH #4 REBAR TOP AND BOTTOM 12-4 13-0" 26-8" 3 EACH #4 CONT. REBAR 1-0" 28-0 I 2-0"
2. For the figures shown, calculate how many cubic yards of concrete are needed to construct the continuous footing and
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
2. For the figures shown, calculate how many cubic yards of concrete are needed to construct the continuous footing and
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!